Polimex-Mostostal concluded a contract worth over PLN 192 mln for the construction of a stadium in Zabrze
25-08-2011
Today, on 24 August 2001 Polimex-Mostostal S.A. concluded with the Stadium in Zabrze Sp. z o.o. a contract for modernisation of the Ernst Pohl stadium in Zabrze Stage I.
Contract net value: PLN 156,503,945.56
Contract gross value: PLN 192,499,853.04
Polimex-Mostostal SA is the general contractor of the investment.
Works completion date: April 2013.
The scope of the contract for modernisation of the Ernst Pohl stadium in Zabrze Stage I covers a/o:
- dismantling of existing installations, ground tribune and technical
buildings in particular,
- construction of new tribunes: northern, eastern and southern as well as
roofed corners,
- construction of an underground garage located under the main entrance square,
- land development along with Olimpijska Street reconversion.
Some information on the facility:
- number of spectator seating: 24 699 (31 319 seatings targeted (stage I + II)),
- number of garage places in the underground garage: 1188,
- quantity of concrete of different types used for construction: about 50 000 m3,
- weight of reinforced steel: about 7 000 tons
- weight of constructional steel of the roofing: about 1 700 tons
The top level of the stadium will be made in monolithic reinforced concrete construction, the tribune steps – prefabricated, the roofing in steel construction. Roof covering of trapezoidal sheet and polycarbonate. Building body elevation made of aluminum tubes.